zone pumps to zone valve conversion.
Generally the decision to zone with pumps or valves comes down to personal preference, and maybe past experiences.
When you see an installation with a wall of zone pumps, maybe 4 or more, that system is probably over-pumped. 6 zone pumps on an 80K boiler would be an example. All pumps running way to the bottom of their curve with wire to water efficiency below 20% on a common PSC type circulator.
With the acceptance and wide availability of ECM delta P type circulators, the potential to drop considerable power consumption and have better flow control over the zones could be an option.
A backup pump piped in or on the shelf could ease the worry of a single pump causing the entire system to be down.
Siggy had this thought so I built up a prototype.
Thoughts or suggestions?
trainer for Caleffi NA
Living the hydronic dream
Comments
-
Was it very tricky to get the same port to port length as the pump or did you get it first try?
0 -
Pretty cool idea. I did something similar for flushing older systems. I made up a straight pipe with two flanges (connected to iso flanges) to flush the system, initial purge it, then swap out the blanks for circulators. To me I think it's a way to keep junk getting lodged into impellers.
0 -
pump spacers, handy for piping systems for the correct spacing
, too
Bob "hot rod" Rohr
trainer for Caleffi NA
Living the hydronic dream0 -
Yeah, it took a few flange brand tries:) This is where BSP threaded pipe shines, Loctite or hemp the threads and stop wherever you want.
A copper sweat version is pretty easy to get "exact", but the sweat flanges are more$$
Bob "hot rod" Rohr
trainer for Caleffi NA
Living the hydronic dream0 -
Where do i put in an order for these?
0 -
Neat idea and all, but don't we need to repipe anyway to add a system circ?
0 -
I prefer pumps to valves, especially when pump has integral check valve. Can be difficult to find circulators small enough. Used to be positive displacement pumps sold for this purpose.
0
Categories
- All Categories
- 87.4K THE MAIN WALL
- 3.3K A-C, Heat Pumps & Refrigeration
- 61 Biomass
- 430 Carbon Monoxide Awareness
- 122 Chimneys & Flues
- 2.1K Domestic Hot Water
- 5.9K Gas Heating
- 115 Geothermal
- 168 Indoor-Air Quality
- 3.8K Oil Heating
- 78 Pipe Deterioration
- 1K Plumbing
- 6.5K Radiant Heating
- 395 Solar
- 15.8K Strictly Steam
- 3.4K Thermostats and Controls
- 56 Water Quality
- 51 Industry Classes
- 50 Job Opportunities
- 18 Recall Announcements