Finally all the piping is done, pressure holding. I used a bunch of old, recycled fittings. That can be frustrating.
Buffer has two curved low loss header pipes. Lochinvar 55 Knight boiler feeds on the 1". Radiant pulls from the 3/4. HX separates glycol in the HP from the buffer tank and system piping.
Boiler supply comes out through air separator to a 3 way zone valve. Normal operation flows to buffer tank. A dual coil solar tank will be is supplied from the other port of the 3 way ZV on dhw priority call.
The radiant is also a 3 way zone valve. In heating season the Alpha runs 24/7. When the Ecobee stat calls for shop heat, the valve opens to the buffer tank.
Piping will be supported after insulation is installed.
Some of the tools I used to bend the copper and T-Drill the curved header pipes. they are probably older than some of the people on this list😉
On to the wiring.
trainer for Caleffi NA
Living the hydronic dream
Comments
-
nice work! What’s the red item hanging on wall next to boiler?
0 -
Categories
- All Categories
- 87.9K THE MAIN WALL
- 3.3K A-C, Heat Pumps & Refrigeration
- 60 Biomass
- 430 Carbon Monoxide Awareness
- 136 Chimneys & Flues
- 2.2K Domestic Hot Water
- 6K Gas Heating
- 124 Geothermal
- 170 Indoor-Air Quality
- 3.9K Oil Heating
- 80 Pipe Deterioration
- 1.1K Plumbing
- 6.7K Radiant Heating
- 397 Solar
- 16.2K Strictly Steam
- 3.5K Thermostats and Controls
- 56 Water Quality
- 52 Industry Classes
- 51 Job Opportunities
- 18 Recall Announcements