Work in Progress

Options
Paul Pollets
Paul Pollets Member Posts: 3,656
edited May 2022 in THE MAIN WALL
Large home renovation with RFH, Pool/Spa HX's, Make-up air and DHW using Viessmann Vitodens B2HA 530 and Dekamatik 300; Vitocell 79g 300 tanks going in next week.


TinmanRich_49

Comments

  • pedmec
    pedmec Member Posts: 973
    Options
    looks good except all the accessories should have been installed on the system side
  • Paul Pollets
    Paul Pollets Member Posts: 3,656
    Options
    Accessories?
  • Tinman
    Tinman Member Posts: 2,808
    Options
    pedmec said:
    looks good except all the accessories should have been installed on the system side
    If you’re referring to the make-up water and the expansion tank, the location is more than fine. 
    Steve Minnich
    GGrossIronmanRich_49
  • GGross
    GGross Member Posts: 1,048
    Options
    Great work!
  • hot_rod
    hot_rod Member Posts: 22,143
    Options
    Nice work Paul. This the job you were looking for the 2-1/2" Sep 4 for?
    Bob "hot rod" Rohr
    trainer for Caleffi NA
    Living the hydronic dream
  • Paul Pollets
    Paul Pollets Member Posts: 3,656
    Options
    Yes, we couldn't get our hands on the Caleffi model, which was back ordered.