Replacement for the LightRay Furnace

Ironman
Member Posts: 7,684
This is where we started (as previously posted in another thread):

And this is where we are now:


Along the way:




This system was a combination of a 120+ year old one and two pipe air vent system. One of the returns would not hold air pressure and was inaccessible; so, we did a modification and eliminated that return and one first floor rad and re-worked the branch feeding the other rad's to drain counter Flow:


Two Big Mouth vents clear the 80' 2 1/2" main in less than three minutes.




And this is where we are now:


Along the way:




This system was a combination of a 120+ year old one and two pipe air vent system. One of the returns would not hold air pressure and was inaccessible; so, we did a modification and eliminated that return and one first floor rad and re-worked the branch feeding the other rad's to drain counter Flow:


Two Big Mouth vents clear the 80' 2 1/2" main in less than three minutes.



Bob Boan
You can choose to do what you want, but you cannot choose the consequences.
You can choose to do what you want, but you cannot choose the consequences.
1
Comments
-
-
So this is the exact same boiler as the lennox GSB?
And it worked well with the 2 2inch risers?0 -
225,000 BTUH input with 7 sections?
And a 3" header?0
Categories
- All Categories
- 86.7K THE MAIN WALL
- 3.1K A-C, Heat Pumps & Refrigeration
- 56 Biomass
- 423 Carbon Monoxide Awareness
- 104 Chimneys & Flues
- 2K Domestic Hot Water
- 5.6K Gas Heating
- 103 Geothermal
- 159 Indoor-Air Quality
- 3.6K Oil Heating
- 69 Pipe Deterioration
- 944 Plumbing
- 6.2K Radiant Heating
- 385 Solar
- 15.3K Strictly Steam
- 3.4K Thermostats and Controls
- 54 Water Quality
- 43 Industry Classes
- 47 Job Opportunities
- 18 Recall Announcements