Snowmelt Design
Korean_Redneck
Member Posts: 1
I am working on a Senior Design Project on a snowmelt system for a runway. I need some help figuring the heat required in the pipes and how far apart the pipes need to be to effectively melt the snow. Also, I need to know if I need a reheater or additional heat exchanger in order to keep the required temperature. The sample size of the runway I am using is 150 ft wide by 1000 ft long.
Info to take acct
1. Snowfall rate up to 3.5 in/hr
2. Average air Temp at 16 F (-8.89 C)
3. Layers -> Pipe - 2 in. NWT Concrete - 2 in Asphalt
4. Pipe is PEX (HDPE)
5. Mixture in pipes is propylene glycol and water (40%:60%)
6. Pipe - ID - 1 in, OD - 1.125 in
7. Pipe will run parallel with the runway
Thanks!
Info to take acct
1. Snowfall rate up to 3.5 in/hr
2. Average air Temp at 16 F (-8.89 C)
3. Layers -> Pipe - 2 in. NWT Concrete - 2 in Asphalt
4. Pipe is PEX (HDPE)
5. Mixture in pipes is propylene glycol and water (40%:60%)
6. Pipe - ID - 1 in, OD - 1.125 in
7. Pipe will run parallel with the runway
Thanks!
0
Comments
-
Starting point
This should help get you started
http://www.uponorpro.com/~/media/Extranet/Files/manuals/SIMeltMan2003.aspx?sc_lang=en"If you can't explain it simply, you don't understand it well enough"
Albert Einstein0
This discussion has been closed.
Categories
- All Categories
- 86.6K THE MAIN WALL
- 3.1K A-C, Heat Pumps & Refrigeration
- 54 Biomass
- 423 Carbon Monoxide Awareness
- 98 Chimneys & Flues
- 2K Domestic Hot Water
- 5.5K Gas Heating
- 101 Geothermal
- 157 Indoor-Air Quality
- 3.5K Oil Heating
- 66 Pipe Deterioration
- 931 Plumbing
- 6.2K Radiant Heating
- 384 Solar
- 15.2K Strictly Steam
- 3.3K Thermostats and Controls
- 54 Water Quality
- 43 Industry Classes
- 48 Job Opportunities
- 17 Recall Announcements