snow melt labor
Matt_21
Member Posts: 140
of snowmelt could 2 men lay down in a day on average. the attahment would be to wire mesh already laid down. also, is insultarp the way to go over polystryene for insulation?
0
Comments
-
RUFF EST.
I normally allow for 100SF per man hour.
2-Men, 8 hours = 1600SF, laid, tied into manifold & pressure test on.
of course individuals work at different paces. Best to track your men-hours & soon you will have an accurate SF per Man-Hour figure..
hope this helps...
0
This discussion has been closed.
Categories
- All Categories
- 86.6K THE MAIN WALL
- 3.1K A-C, Heat Pumps & Refrigeration
- 54 Biomass
- 423 Carbon Monoxide Awareness
- 99 Chimneys & Flues
- 2K Domestic Hot Water
- 5.5K Gas Heating
- 101 Geothermal
- 157 Indoor-Air Quality
- 3.5K Oil Heating
- 66 Pipe Deterioration
- 932 Plumbing
- 6.2K Radiant Heating
- 384 Solar
- 15.2K Strictly Steam
- 3.3K Thermostats and Controls
- 54 Water Quality
- 43 Industry Classes
- 48 Job Opportunities
- 17 Recall Announcements