I have a small commercial boiler Weil McLain LGB650 (650,000 input) I need to replace but the boiler is 30+ weeks out. I cant find anything available and I don't have enough room to twin smaller cast boilers. This feeds 3 fan coils and some baseboard radiation. My question is would a condensing boiler make sense. I am concerned that running at high temperatures would lose the efficiency and shorten the life of the boiler. I am also concerned about the flow. I currently has 2 circulators with a flow rate of 40 gpm each. I think that would be a problem even if it's piped with primary/secondary.
I really would like the simplicity of the cast boilers.
I will be consulting with my distributers tech department but value your guys opinions.
Thanks in advance.
I really would like the simplicity of the cast boilers.
I will be consulting with my distributers tech department but value your guys opinions.
Thanks in advance.
0
Comments
-
It's a common misconception that high temperatures at design temperature harm efficiency over the course of a year. If the fan coils/baseboard can return condensing temps for 95% of the year (guessing!) efficiency will be fine! That's assuming the baseboard and fan coils actually need the highest temps on design day. That's usually not the case if the original heat loss was botched, which it typically was.1
-
That could also mean they don't need a boiler with 650k of capacity, which could help the lead time issue, if true.Hot_water_fan said:It's a common misconception that high temperatures at design temperature harm efficiency over the course of a year. If the fan coils/baseboard can return condensing temps for 95% of the year (guessing!) efficiency will be fine! That's assuming the baseboard and fan coils actually need the highest temps on design day. That's usually not the case if the original heat loss was botched, which it typically was.
3 -
I understand that. In this case it is a school. They like to do setback when the school is out. Then recover before it reopens. Would it make sense to just allow more time to recover to maintain the lower water temp? Maybe I just answered my own question.
Thanks0 -
@airhead that or use a wider delta T. A delta T of 13 is tight!0
Categories
- All Categories
- 86.3K THE MAIN WALL
- 3.1K A-C, Heat Pumps & Refrigeration
- 53 Biomass
- 422 Carbon Monoxide Awareness
- 90 Chimneys & Flues
- 2K Domestic Hot Water
- 5.4K Gas Heating
- 100 Geothermal
- 156 Indoor-Air Quality
- 3.4K Oil Heating
- 63 Pipe Deterioration
- 917 Plumbing
- 6.1K Radiant Heating
- 381 Solar
- 14.9K Strictly Steam
- 3.3K Thermostats and Controls
- 54 Water Quality
- 41 Industry Classes
- 47 Job Opportunities
- 17 Recall Announcements