Completed boiler & chiller instal
Henry
Member Posts: 998
This was a complete replacement of the boilers and chillers in a 32 floor building in Old Montreal. There are 7 colours of vinyl cladding of the insulation of which 3 were special order. I took the pictures last week. One of the chillers was working as the South side of the building was getting sun. There are a 36 Armstrong pumps. It was a 1 year project.
0
Comments
-
Beautiful
Nice work! Wow!0 -
wow- the bar has been set high!
very impressivegwgillplumbingandheating.com
Serving Cleveland's eastern suburbs from Cleveland Heights down to Cuyahoga Falls.0 -
What
was there before?All Steamed Up, Inc.
Towson, MD, USA
Steam, Vapor & Hot-Water Heating Specialists
Oil & Gas Burner Service
Consulting0 -
New install.
WOW ! Very very nice! I'm drooling here.lol. How about a breakdown of all of those colored pipes!! Whats inside of them? What type of facility?0 -
New install.
Twitchy finger.0 -
Very Impressive
Nice work...0 -
review
I think in 2nd pic from top, I see a screw that is a 1/2 turn loose0 -
!!!!
Very nice. It's so rare that there's money in the budget to do that nice of a job. You should be very proud.0 -
Seven colors?
Hot water supply
Hot water return
Cold water supply
Cold water return
Cold air
Hot air (politicians floor)
Sewage ditto
Hopefully the south side chillers were pumping their heat into the north side--NBC0 -
bedroom
In the corner so I could live there? That is beautiful!0 -
NICE
and they say there is no good help left. BEAUTIFUL0 -
Tower
It is an office tower that had two fire tube Volcano boilers. I has actually 8 colours of vinyl covering. BTW, all the pumps have drives on them. The control contract alone was $2 million. There is also some free cooling using a large plate heat exchanger. There are two water towers. I have previously posted pictures of the 800 ton crane loading one tower, the chillers and pumps. We had cut a hole in the roof to remove the old and drop in the new. On a second occasion, we lifted the North side water tower and the boilers. We are presently replacing the water towers and chillers of the Olympic village two residence complexes0 -
Pumps
Nice looking work. Are the pumps on VFD?0 -
Pumps
Yes, VFD0
Categories
- All Categories
- 86.3K THE MAIN WALL
- 3.1K A-C, Heat Pumps & Refrigeration
- 53 Biomass
- 422 Carbon Monoxide Awareness
- 75 Chimneys & Flues
- 2K Domestic Hot Water
- 5.4K Gas Heating
- 93 Geothermal
- 150 Indoor-Air Quality
- 3.4K Oil Heating
- 64 Pipe Deterioration
- 920 Plumbing
- 6.1K Radiant Heating
- 373 Solar
- 15K Strictly Steam
- 3.3K Thermostats and Controls
- 50 Water Quality
- 39 Industry Classes
- 47 Job Opportunities
- 17 Recall Announcements